AQW 27315/17-22 Written question to the Minister of Education

To ask the Minister of Education to provide a timeframe in which the outstanding task orders at Crumlin Integrated Primary School will be completed.

Asked by John Blair MLA on 13 December 2021

  • Answered
  • Written
  • After due date
Tabled
13 December 2021
Answer due by
31 December 2021
Answered
6 January 202224 days after tabling
Department
Department of Education
Priority question
No

Answer

Crumlin Integrated Primary School (IPS) submitted three applications under the November 2017 Minor Works Call for: access control improvements; heat improvement measures; and toilet upgrades. These did not rank high enough to progress at the current time and will remain on the Call list to be progressed on a priority order basis, as and when funds become available.

The school meals accommodation at Crumlin IPS has been identified within Tranche 2 of the Strategic Investment in School Meals Accommodation Programme. It is anticipated that planning for this Tranche will commence in the 2022/23 financial year.