AQW 24404/17-22 Written question to the Minister of Agriculture, Environment and Rural Affairs
To ask the Minister of Agriculture, Environment and Rural Affairs what capacity is remaining in Cottonmount Landfill Site.
Asked by John Blair MLA on 15 October 2021
- Answered
- Written
- Tabled
- 15 October 2021
- Answer due by
- 1 November 2021
- Answered
- 1 November 202117 days after tabling
- Priority question
- No
Answer
I can advise that the Cottonmount Landfill, Mallusk, has a remaining capacity of approximately 420,000 m3 within its current constructed engineered cells. The site’s Permit (P0090/05A) provides for the construction of additional cells which would realise approximately 4.2 million m3 of void space.