AQW 29365/17-22 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure, pursuant to AQW 27597/17-22, when resurfacing of the Largy Road in Crumlin will commence.
Asked by John Blair MLA on 7 February 2022
- Answered
- Written
- Tabled
- 7 February 2022
- Answer due by
- 22 February 2022
- Answered
- 14 February 20227 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
Phase 1 of the resurfacing scheme on Largy Road, Crumlin, running between Crumlin Road and House No.42B, commenced on 18 January 2022 and is due to be completed by the end of February 2022.
My officials have advised it is their intention to complete Phase 2, from House No.42B to the end, as part of the 2022/23 work programme, subject to the availability of funding.