AQW 29365/17-22 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure, pursuant to AQW 27597/17-22, when resurfacing of the Largy Road in Crumlin will commence.

Asked by John Blair MLA on 7 February 2022

  • Answered
  • Written
Tabled
7 February 2022
Answer due by
22 February 2022
Answered
14 February 20227 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

Phase 1 of the resurfacing scheme on Largy Road, Crumlin, running between Crumlin Road and House No.42B, commenced on 18 January 2022 and is due to be completed by the end of February 2022.

My officials have advised it is their intention to complete Phase 2, from House No.42B to the end, as part of the 2022/23 work programme, subject to the availability of funding.