AQW 29741/17-22 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure for an update on the upgrade of the Mossley West railway station.

Asked by John Blair MLA on 14 February 2022

  • Answered
  • Written
Tabled
14 February 2022
Answer due by
1 March 2022
Answered
21 February 20227 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

I am ambitious for our rail network, and am keen to do all that I can to explore how we can progress rail improvements within the budgetary envelope that is available to me.

I am pleased to advise that the planning approval for a new 240 space Park & Ride facility at Mossley West Train station has been granted. The Translink project team will now commence the procurement process to appoint a main contractor with a view to construction commencing in Autumn 2022 with an estimated completion date of Autumn 2023.

Official sources