AQW 3767/22-27 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure for an update on the provision of cycle lanes on the Scullions Road, Newtownabbey.
Asked by John Blair MLA on 29 September 2022
- Answered
- Written
- Tabled
- 29 September 2022
- Answer due by
- 14 October 2022
- Answered
- 14 October 202215 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
My Department is developing a footway/cycleway scheme on Scullion’s Road and Sandyknowes Roundabout to link Ballyhenry Road with Mullusk.
The first phase, which is programmed to start later this year, involves the construction of a segregated cycleway and footway on the existing footway and verge between Mallusk Road and a point 130m south of Sandyknowes Roundabout.
Should you have any further questions on this matter, please contact DfI Roads Northern Division at: dfiroads.northern@infrastructure-ni.gov.uk.