AQW 16201/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure (i) for an update on the progress of flood alleviation schemes that are currently underway; and (ii) how these schemes are being prioritised.

Asked by John Blair MLA on 4 October 2024

  • Answered
  • Written
  • After due date
Tabled
4 October 2024
Answer due by
21 October 2024
Answered
22 October 202418 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

My Department’s Rivers Directorate currently has over 50 separate potential flood alleviation schemes on its forward looking Capital Works Programme (CWP), with approximately half of these already in progress at various different stages.

Details of these schemes are available on my Department’s website at: https://storymaps.arcgis.com/stories/32cb28e2dc744243bd2d2c48e7245008.

In terms of prioritising flood alleviation schemes, the benefits, in terms of “flood damage avoidance”, must outweigh the actual costs of constructing and maintaining the works for it to be considered an economically viable scheme which can be taken forward.

Cost viable schemes are scored and prioritised before being placed on the Capital Works Programme (CWP). The scoring mechanism broadly assesses the existing degree of flood protection, scheme economics, special considerations, and financial control.

Official sources