AQW 20223/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure for his latest assessment of bringing forward flood alleviation plans following the recent flooding in Antrim town.

Asked by John Blair MLA on 9 January 2025

  • Answered
  • Written
  • After due date
Tabled
9 January 2025
Answer due by
24 January 2025
Answered
29 January 202520 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

My Department is currently in the process of commissioning a consultant to undertake a feasibility study to assess the flood risk from the Sixmilewater River to properties in Antrim, Muckamore and Dunadry. It is currently anticipated that this study should commence early this year and I can advise that such a study would typically take approximately 18 months to complete.

The study aims to identify if there are any economically viable schemes to reduce the impact of river flooding.